Nick Veretisi
Director, Data Center Group Safety Mortenson Construction
Seminars
Tuesday 2nd June 2026
Case Study: Accelerating Schedules Without Sacrificing Safety, Quality or Labor Capacity
2:00 pm
- Using rigorous preconstruction analysis to evaluate owner expectations with actual labor, procurement and sequencing realities within regionally constrained labor markets to prevent unsafe or unbuildable accelerated schedules
- Identifying how to adapt safety protocols for harsh weather, manage fatigue in multi-shift operations and maintain predictable performance while moving fast
- Leveraging six-week look-ahead planning to stay ahead of schedule impacts and taking corrective action before delays stack across scopes on fast-track, multi-scope projects